A token penalty may not deter breach; an excessive one can run into legal limits. Calibrate the amount, define the trigger and check how it interacts with other remedies.

The contractual penalty, known in Mexico as pena convencional, is often copied with little thought about the amount. A round number goes into the agreement; only after a breach do the parties discover whether it addresses the actual risk.

It is a Mexican law mechanism. Do not assume it follows the same rules as a similarly named clause in another jurisdiction.

The problem it addresses

A damages claim usually requires evidence of the loss, its amount and its connection to the breach. Quantifying a disrupted operation or a lost opportunity can be difficult and expensive.

A valid penalty clause can avoid having to prove the amount of loss. It does not remove the need to prove the facts that trigger the clause.

The risk of setting the amount too high

A large figure is not necessarily stronger protection. Under the Código Civil Federal (CCF, Federal Civil Code), the penalty cannot exceed the principal obligation, and partial performance can require a reduction. The applicable legal regime matters. CCF, Articles 1842–1845 (Spanish).

An excessive demand can also undermine the negotiation. The other party may resist the entire clause rather than discuss a workable allocation of risk.

The risk of setting it too low

A token penalty can become the price of breaching the contract. A supplier may prefer to serve a more profitable customer first and absorb a small late-delivery charge.

Consider whether the proposed amount gives the other party a meaningful reason to perform. This commercial assessment still has to fit within legal limits.

How to calibrate the amount

Use three reference points:

  1. The operational cost of the breach. Identify what a delay or failure could interrupt, such as a production line. This helps assess the risk and whether a penalty is the right tool; it does not override statutory caps.
  2. The obligation being secured. Relate the amount to the relevant obligation and applicable limits rather than choosing a multiple of the entire contract price.
  3. A graduated structure where appropriate. A daily or weekly amount with a clear maximum may suit delay better than a single undifferentiated charge.

How to draft the clause

Four points need particular attention:

  • The precise trigger. “Delivery more than five business days late” is clearer than “breach of the agreement,” provided the delivery obligation and exceptions are also defined.
  • Its relationship with other remedies. Article 1840 CCF excludes additional damages when a penalty is stipulated. Article 1846 addresses performance and penalties, including exceptions for delay or defective performance; those exceptions are not a general permission to add damages. Article 88 of the Código de Comercio (Commercial Code) also requires attention to the election between performance and the agreed penalty. CCF (Spanish), Código de Comercio (Spanish).
  • The collection mechanism. Explain notice, payment and any valid set-off arrangement. A deduction mechanism may simplify administration but cannot guarantee that a dispute will never reach court.
  • A maximum amount when the penalty accrues over time.

The danger of overlooking the overall liability allocation

A small penalty drafted as the sole remedy may leave a business poorly protected against a serious failure. Review the clause together with insurance, termination rights, liability limits and the treatment of intentional misconduct under applicable law.

The solution is not simply to label damages “cumulative.” Choose a lawful structure for the actual risk before signing.

The penalty provision is one of the five clauses where contractual risk is concentrated. Draft it for the transaction instead of copying an amount from another agreement.

FAQ

Frequently asked questions

Related topics

#Contractual penalties#Contracts#Breach of contract

Author

Emanuel Isaid Escobar López

Founding & Managing Partner · Corporate, Tax & Administrative Law

Emanuel Isaid Escobar López

Emanuel founded Hyperion Derecho & Negocios in 2019 with a clear conviction: businesses operating in San Luis Potosí and the Bajío deserve first-rate legal advice, a business perspective and direct access to a partner. He has led the firm and its corporate, tax and administrative law practice ever since.

Found this useful? Share it

Keep reading

Related articles

View all

Free consultation

Does your company need to address this?

Tell us what is happening. We will explain how urgent it is and how we would approach it. The initial assessment is free.

Assess your matter